Highbury Magistrates Court

Client: Her Majesty’s Court Services
Value: £880k
Date: March 2011

Spring 2011 saw the completion of our asbestos remediation and building reinstatement works at Highbury Magistrates Court. The works were split into 10 zones (comprising of courts, custody areas and offices) and were carried out in a phased manner – leaving the remaining courts in use. The works involved the removal of ceilings under controlled conditions, the removal or encapsulation of asbestos and the reinstatement of suspended ceilings with laminate timber panels.

Through careful programming and close liaison with the client the works we re-sequenced and completed two weeks ahead of schedule.