11 Southwark Street

Client: Rosemont Investments
Value: £2m
Date: January 2015

This project with Rosemount Investments involved the conversion and extension of an existing office building to create ground floor space for a restaurant and retail unit and the creation of 7 nr flats on the upper floors.

The works comprised the demolition from the 4th floor down to the 1st floor. This was rebuilt up to 5 storeys, with the erection of a new rear extension from the 1st to 3rd floors, with a mansard roof extension from the 4th to the 5th floor.

Restricted access to the project made the installation of 106 mini piles in the basement challenging. The piles were used to retain existing foundations prior to demolition.

Throughout the building of this project we had to remain flexible to the continuous design improvements.

The project achieved a Breeam Very Good rating.